InterGroup works with rate review panels, public utilities, or customers to support their activities in regulatory rate reviews, including technical analysis, drafting and reviewing information requests, consideration of cross-examination issues, and providing independent observations and recommendations.

SaskEnergy Delivery Service Rate Application

Client
Saskatchewan Rate Review Panel (Saskatchewan)

Dates
2013

Team
Andrew McLaren, Mona Pollitt-Smith

InterGroup was retained as the technical consultant for the Saskatchewan Rate Review Panel’s (SRRP) review of SaskEnergy’s 2013 Delivery Rate Application.

Services provided by InterGroup included reviewing and analyzing the Delivery Rate Application to identify key issues, drafting and reviewing information requests to SaskEnergy, and providing an independent consultant report with observations and recommendations to the SRRP.

For more info contact: Andrew McLaren


Bluefish Dam

Client
NWT Power Corporation (NWT)

Dates
2010 - 2011

Team
Patrick Bowman, Hayitbay Mahmudov

InterGroup participated in the development of the business case and the project permit application for the original purchase of the Bluefish generating station by NTPC. When the Bluefish generating station required a dam replacement in 2010/11, InterGroup participated in all project licensing activities, including appearing as an expert witness before the Mackenzie Valley Land and Water Board.